1. Mode d'emploi — what LTkr synthesises
LTkr (Last Tracker) is the collaborative layer that keeps industrial promises visible: who owns what, this week’s meeting frame, what was decided, and — when delivery slips — a calm, non-blame explanation.
- Shared task board — actions with owners, due dates, categories (HSE, C&P, logistics…), status and notes.
- Meeting agenda — timed weekly structure (Last Planner results, supply chain, JV, milestones…).
- Meeting minutes (MoM) — decisions, issues, attendance, actions reviewed.
- Variance explanations — simple, non-conflictual reasons why a resolution plan did not hold (not a court case).
- Priority colours — so the room sees critical vs base work at a glance (see §2).
How to use on this site: open the live workspace (editable in the browser), or the Kapuni read-only demo; present the DFKPS deck in the room; export agenda / minutes / progress; send reminders with mailto (your mail client).
What Grok / this site can do now: agenda prep, colour-coded actions (red / orange / blue / gray), online acceptance ticks, minutes draft, progress board, export files, e-mail drafts via mailto:. Not yet (needs server / product backend): automatic multi-user sync, authenticated acceptance workflow, scheduled SMTP mail without opening a mail client, full offline native app install.
2. Task classification · colours
Four levels — red · orange · blue · gray (critical · important · base · simple info).
Simple info · gray
Base · to do
Important · medium
Critical
- Simple info — lilac · FYI, closed items, context only — no pressure on the room.
- Base — blue · standard work to execute this week.
- Important — orange · medium priority, in progress or near due.
- Critical — red · blocked, safety, JV decision, or path-critical package.
3. Why the resolution plan did not hold (10–12 calm reasons)
Variances are written as simple, non-conflictual explanations — facts, not accusations. Typical catalogue (Last Planner / industrial practice):
- Prerequisite not ready (upstream deliverable late)
- Underestimated effort or complexity
- Incomplete or poor-quality input data
- External decision pending (JV / client / authority)
- Resource not available (people / equipment)
- Priority re-sequenced by the team
- Scope clarification needed
- Contractor / supply-chain delay
- Weather or site access constraint
- Safety hold / permit not yet in place
- Interface misalignment between disciplines
- Plan optimistic vs real site conditions
In the Kapuni demo, each variance links an action, an owner, a date and a category code (e.g. lack_of_decision, poor_data_quality, underestimated_effort).
Coming soon
JSON package / tracker export
Live JSON data, Kapuni export and interactive board are hidden until the full LTkr product release. Mode d'emploi and DFKPS presentation remain available.
5. Export package & privacy
The Kapuni package ships under outils/ltkr/ with MANIFEST, NOTICE-RGPD, DFKPR splash images and split JSON entities.
data/tracker.json — full snapshot (re-import into LTkr)
data/actions.json · agenda.json · meetings.json · variances.json · …
DFKPR/*.jpg — text-free covers for DFKPS / dossiers
Anonymized export: technical member IDs are kept for link integrity; names, emails and organisations are pseudonyms. See NOTICE-RGPD.md.
Package README